Street and Water Main Replacements

10 Mile Sanitary Relief Sewer Road Project (Jefferson to Little Mack)
Beginning the week of April 13th, the contractor will be starting the construction of a new sanitary relief sewer on Ten Mile Road from Jefferson to Little Mack.  The interceptor line will be installed using micro-tunneling technology.  The contractor will be excavating approximately 7 shafts along the route to insert tunneling equipment and pipe.  Ten Mile Road will be a single lane, one-way east bound only (Harper to Jefferson).  Jefferson will be reduced to two lanes (bi-direction traffic from just south of Revere to just north of Maple).  The first phase will start at Jefferson and work west to Harper.

9 – Mack Water Main

Completed – Doing some patches in the parking lot.

 9 – Mack Repaving Project

They are starting Phase I Mack to the curve on Colony.

12 Mile Water Main Replacement (Jefferson to Harper)

The City of St. Clair Shores has contracted with DiPonio Construction to install a new water main on 12 Mile from Harper to Jefferson.  Traffic controls and water main materials are scheduled to be delivered the week of September 18th with construction starting the week of September 25th.  The work will consist of installing a new water main on the north side of the road either in the greenbelt or under the sidewalk depending on the amount of right-of-way available. 

2017 Local Paving Project – Clairwood St. (Jefferson to the Lake)

Florence Cement has completed the pouring of the driveway approaches.  Access to your driveway will be permitted in approximately 5-7 days.  Please do not remove the barricades yourself as using the approach prior to proper cure time will void any warranty.  The contractor has scheduled restoration of any damaged irrigation systems beginning October 11.  Once the lines and sprinkler heads have been installed they will coordinate with you to turn on the system to insure everything is restored and working properly.

2017 Local Paving Project – Beste (Gafke to 12 Mile Rd.)
Florence Cement will begin removing the pavement on the east side of Beste beginning October 13, 2017.  Once the pavement is removed, underdrainage will be installed and stone base in preparation of paving.  This will take approximately 7-10 days, weather depending.  For those effected by the removal of the pavement on the east side of the road please park on the adjacent side street. 

2017 Local Paving Project - Malvern (Colony to Clairwood)

Florence Cement Company is scheduled to start pavement removal on Monday, October 2nd.  During the period of time in which residents are displaced from accessing their driveway, parking on the adjacent street overnight is permissible. 

 